Subscribe by Email

Articles Posted in Arbitration and Mediation

A recent ruling by the Fifth District Court of Appeal demonstrates the potential ramifications of ambiguities in the mediation and arbitration provisions of construction contracts. The ruling found the lower court correctly determined that the parties had a valid agreement to arbitrate certain claims because the contract clearly required arbitration for claims arising before final payment was due. However, it was silent regarding the procedure for resolving claims arising after the final payment became due, so the case was remanded back to the lower court for a determination as to whether the claims arose before or after final payment was due.

In Royal Palms Senior Apartments Limited Partnership v. Construction Enterprises Inc. et al., Royal Palms appealed the nonfinal order entered in favor of Construction Enterprises Inc. staying the developer’s lawsuit pending mediation and arbitration based on its assertion that the trial court erred in finding a valid arbitration agreement existed and its claim was subject to arbitration.

5DCA-300x183The Fifth DCA affirmed lower court’s finding that the parties had a valid agreement to arbitrate certain claims. However, because it is unclear whether Royal Palms’ claim was one subject to arbitration, it remanded the case for a determination of that issue.

The parties entered into a contract in 2006 for CEI to build the Royal Palms Senior Apartments. The agreement was comprised of the “AIA Document A201-1997 General Conditions of the Contract for Construction” (“General Conditions”) and a supplementary document (“Supplementary Conditions”), which modified and deleted portions of the General Conditions and controlled if the two documents conflicted.

Continue reading

Steve Siegfried 2013 srhl-lawFirm partners Steven M. Siegfried, Stuart Sobel and Berenice M. Mottin-Berger were featured in an article about their work on behalf of one of the firm’s construction clients that appeared in today’s Daily Business Review, South Florida’s exclusive business daily and official court newspaper.  The report, which was titled “Caribbean Construction Firm Scores $4M Judgment,” chronicles the highly contentious litigation and arbitration that led their securing a $4.3 million judgment against DeVry Education Group (NYSE: DV) for Moorjani Caribbean Ltd., a Barbados-based construction company.  The article reads:

Stuart Sobel 2013-thumb-180x270-86799Coral Gables lawyers won a $4.3 million award against a subsidiary of for-profit college company DeVry Education Group in what they say was one of the nastiest arbitration battles they’ve ever fought.

Barbados-based construction company Moorjani Caribbean Ltd. sued over alleged underpayment for the construction of student housing and classroom projects at DeVry’s St. Kitts veterinary school.

Although both parties admitted some aspects of their work relationship was relaxed, with unsigned contracts and loose deadlines, the father-and-son construction company claimed it submitted detailed accounting for both projects and spent years trying to get payment before filing suit.

DeVry Medical International Inc. fought back with counterclaims, alleging it spent more than $1 million fixing design and construction defects in Moorjani Caribbean’s work on the student housing project.

BerenicMottinBergerBut arbitrators found DeVry made improvements to the residence hall so that it could qualify as a place of refuge during a hurricane, not because of deficient construction.

By the time the 2009 bills for the two projects came to the arbitration panel this year, interest and attorney fees made the award much larger than it might have been, Moorjani Caribbean’s lawyers said. Interest on the award continues to grow at a rate of about $593 per day, according to the Aug. 19 final arbitration award.

Continue reading

Stuart Sobel 2013-thumb-180x270-86799Firm shareholder Stuart Sobel authored a guest column that appeared in the May issue of Construction Executive magazine, one of the leading construction industry trade publications in the country.  His article, which was titled “Dispute Review Boards: An ADR Technique That Works,” focused on the use of DRBs for major projects as an effective means to avoid or resolve disputes that may arise during construction.  Stuart’s article reads:

Disputes are endemic to the collaborative nature of construction. It seems prudent to anticipate the disputes, even where the precise nature of the dispute is unknowable, and create a structure for proactively addressing and resolving them when they do arise. Traditional dispute resolution, whether arbitration or litigation, when invoked at the end of the project, takes place too late to save it or get it back on track. Instead, proactive onsite real-time dispute resolution is warranted to protect working relationships, cash flows and schedule progress.

Arbitration has become the preferred alternative dispute resolution forum for resolving construction disputes because it is private, streamlined and presided over by experienced construction professionals.

However, just as with litigation, arbitration only comes into play after a dispute has ripened. The arbitration process usually extracts a considerable toll on the project participants through damaged relationships and expenses. The parties involved are very unlikely to continue doing business together in the future. In addition, discovery in arbitration proceedings is now wider, longer and more expensive, and its growing resemblance to litigation has become unmistakable. Thus, despite its reputation as a cheaper alternative to litigation, arbitration has become more expensive as the process permits more litigation-like discovery, with attendant administrative costs and arbitrators’ fees.

Instead, consider the scenario where an independent person or board, respected by all project participants, is designated in the operative construction contracts to stay abreast of the design and construction and to attend and observe all pertinent meetings (owner/architect/contractor meetings, change order meetings and even important contractor/subcontractor meetings). Through this process, the dispute resolution neutral or, where there is more than one, the Dispute Resolution/Review Board (DRB), can quickly understand theConstruction-Executive-Logo nature and genesis of disputes that are blossoming — before they slow or stop the construction progress.

Continue reading

StuartSobel2013.jpgThe firm’s Stuart Sobel has once again written an article that appeared in the annual special report on Alternative Dispute Resolution published by the Daily Business Review, South Florida’s exclusive business daily and official court newspaper. Stuart’s article, which was published in today’s edition of the DBR and also appeared in Texas Lawyer and the Daily Report (Atlanta), focused on the use of formal mediation proceedings to resolve claims involving catastrophic construction accidents. Earlier this year he represented Miami Dade College in a $33.5 million mediated settlement that included 22 defendants for the collapse of a parking garage during construction.

The firm’s Stuart Sobel, Steven Siegfried and Michael Clark represented Miami Dade College in securing a $33.5 million settlement over the partial collapse of its parking garage while it was under construction at the school’s West Campus in Doral in 2012.

A recent ruling by the Fourth District Court of Appeal reiterates that Florida’s courts will favor arbitration when there is a clear arbitration provision in construction contracts, even if the contracts also include a jury waiver provision.In the case of Bari Builders, Inc. v. Hovstone Properties Florida, LLC, a condominium association sued the developer for construction defects, and the developer filed a third-party complaint against Bari Builders (its subcontractor). The subcontract with Bari included both a provision that the parties agreed to binding arbitration to resolve any claim as well as a separate provision stating that “the parties waive the right to jury and agree to determination of all facts by the court.”

Stuart Sobel 2013.jpgThe firm’s Stuart Sobel played a very important role in helping the builder of the new PortMiami Tunnel, which opened for traffic last month, to resolve a significant dispute and avoid a potentially lengthy delay during construction. Stuart served as the lead legal counsel for tunnel builder Bouygues Civil Works Florida, Inc., and he was instrumental in helping the company to secure a $58.5 million settlement that was the subject of a front-page article in the February 5, 2013 edition of the Daily Business Review.

Florida’s Second District Court of Appeal recently issued an important opinion in the case of Snell v. Mott’s Contracting Services, Inc., over the issue of lien rights and the differences between arbitration and litigation.

Arbitration is one of the most common forms of dispute resolution in construction today, but the recent ruling by the Third District Court of Appeal illustrates some of the difficulties that parties to arbitration proceedings can face in appealing or vacating the arbitrator’s award.